Lesson 4 of 4 · 15 min
A 90-day plan
A roadmap with owners, milestones and stop criteria.
Slide 1 of 7
A plan that did not know how to stop
- Twenty six actions, none with an owner
- Delivery milestones, no decision milestones
- At ninety days, nobody knows whether it worked
Sônia runs a condominium management company with ninety employees. She asked an AI for a ninety day plan and got twenty six well written actions: raise leaders' awareness, map processes, engage teams. None had an owner. None said what to do if things went wrong. Three months after following a plan like that, the final meeting becomes an exchange of impressions. A good ninety day plan is shorter. It has few cases, one owner for each and dates when someone is obliged to decide.
Full transcript
A plan that did not know how to stop
Sônia runs a condominium management company with ninety employees. She asked an AI for a ninety day plan and got twenty six well written actions: raise leaders' awareness, map processes, engage teams. None had an owner. None said what to do if things went wrong. Three months after following a plan like that, the final meeting becomes an exchange of impressions. A good ninety day plan is shorter. It has few cases, one owner for each and dates when someone is obliged to decide.
The format: two cases and four dates
Use two cases, chosen by the criteria from the lesson on value. And four dates. On day fifteen, the question is whether it is prepared: owner, baseline, approved tool, written limit. If something is missing, it does not start. On day thirty, whether the test with real cases worked in the small group. On day sixty, what the measurement shows and whether it is worth going on. On day ninety, the decision: expand, adjust or close. Between the dates, the team works. On the dates, leadership shows up, and does not send a representative.
Owners with names, and power to stop
Three roles are enough. The sponsor belongs to leadership, decides budget and limit, and removes obstacles. The owner of the result is the manager of the area where the work happens. That person measures, answers and can stop the use without asking permission. Support brings together those who handle data, security, legal and training, with hours reserved in their calendars. Put a substitute next to each name. Ninety day projects cross vacations, and a plan without a substitute sits still for two weeks without anyone noticing.
Stop criteria written beforehand
Write the stop criteria before you start, when nobody is attached to the project. There are three kinds. The immediate stop applies to harm to someone or personal data outside the approved tool: switch off the same day and investigate later. The quality stop uses a number, such as more than fifteen percent of rework in a sample. The value stop happens when the measured gain is below half of the target. NIST, in the United States, recommends having defined means and responsible people to deactivate a system that behaves outside what was intended.
Beware the enthusiasm of the first weeks
In an experiment with more than seven thousand professionals, use of the tool reached its highest point in the first five weeks. The authors mention training, novelty and trying things out as possible reasons. For your plan, the lesson is simple: the excitement of week four is no basis for signing an annual contract. Wait for the second month's measurement, when novelty has passed and the habit has appeared, or not. And measure work done with quality. The number of logins shows curiosity, and little more than that.
Imagine failure before starting
Gather the group for thirty minutes and say: it is day ninety and the plan failed. What happened? People tell you risks they would not mention in an optimistic meeting: the manager was on vacation, the sample was small, nobody measured the before. For each cause, ask what the first visible sign would be, and put that sign in the plan with a date and an owner. AI helps to widen the list, as long as it receives your plan. Without it, it will list risks that fit any company.
What to do now
Take the one page plan at the end of the lesson. Write the two cases, the names, the measures and the stop criteria. Do the imagined failure exercise with your team and with AI. Then open your calendar and schedule the four decision meetings, with you present. On day ninety, any of the three decisions is a good result, if it comes from measurement. Closing a weak case early frees people and money for the next one. The worst ending is not deciding, and starting another plan on top of this one.
A worked case: Sônia's plan
The request that produced the twenty six actions was:
Build a 90 day plan to roll out AI in a condominium management company.
Sônia threw the result away and wrote her own plan, with two cases: drafts of assembly minutes and drafts of replies to residents. Only then did she call the AI, in another role:
This is my plan. Suppose that, on day 90, it failed. List five causes tied to lines of the plan, with the first sign of each one. Do not add actions.
The answer brought five causes. Sônia sorted them:
| Cause pointed out | Assessment | What changed |
|---|---|---|
| Only 6 assemblies in the period, small sample | Valid | Redo 12 old minutes as well and compare |
| Service manager on vacation in weeks 5 and 6 | Valid | Substitute named |
| No measurement of current reply time | Valid | Two weeks of baseline before day 15 |
| Residents' resistance to AI | Not applicable | Every reply goes out signed by a person |
| High cost of licenses | Already covered | Budget by stage in the plan |
The plan stayed on one page: three corrections and no new front.
What happened on the dates
- Day 15. It started with a baseline: 4 hours per set of minutes, checking included, and 12 minutes per reply.
- Day 30. The test with five people showed a repeated error: the AI applied one condominium's rule to another.
- Day 60. Minutes: 1 hour and 50 minutes, with 8% rework. It goes on. Replies: 11 of 50 with rework, 22%, above the 15% limit. Pause.
- Day 75. With each condominium's rules in the knowledge base, a new test: 6 of 50, or 12%. It returns, only for payment slips, party room bookings and moves.
- Day 90. Expand the minutes to the whole company. Keep the replies on three subjects and measure for one more month.
The pause on day 60 earned a complaint from the team and saved a bigger problem. With the criterion written in March, nobody had to argue in May about whether 22% was a lot.
What goes into the meeting on each date
Three sheets and thirty minutes: the measurement against the target, the errors seen and the request for a decision. The owner of the result presents. The sponsor's question is always the same: if we were starting today, knowing what we know, would we start? If the answer is no, close it and record what you learned.
Exercise
Build and attack your one-page plan
Write a 90 day plan with two cases and use AI to imagine failure and find what is missing.
Step by step
- Fill in the one-page template with two cases from your area, using roles instead of people's names.
- Send the plan with the starter text, in an approved tool.
- Mark each cause the AI pointed out as valid, already covered or not applicable, with the reason.
- Fix the plan: at least one stop criterion, one substitute and one measure.
- Put the four decision dates in your calendar.
Starter text
This is my 90 day plan. Suppose it is day 90 and it failed. 1. List the five most likely causes, each one tied to a line of my plan. Copy the line. 2. For each cause, say the first sign I would see and in which week. 3. Point out what has no owner, no substitute, no measure or no stop criterion. 4. Do not add actions. If you suggest a change, say what I would remove in its place. Plan: [paste here]
How to tell if it's good
- The plan fits on one page and has two cases
- Each case has an owner, a substitute, a baseline, a target and the four dates.
- Stop criteria with a number or a fact
- There is an immediate stop, a quality stop and a value stop, and anyone could say whether each was reached.
- Evaluated the causes the AI pointed out
- Marks at least one as valid and one as not applicable, with a reason from the person's own context.
- Fixed the plan
- Shows the passage before and after at least one change.
Do not use personal data or confidential information in the exercise.
Check
Four situations. Three right answers complete the lesson, and you can try again.
Take away
90 day plan on one page
Template
90 DAY PLAN Start: [date] Sponsor: [name] Substitute: [name] CASE 1: [task] CASE 2: [task] Owner of the result: [name] Owner of the result: [name] Substitute: [name] Substitute: [name] Baseline: [number] Baseline: [number] Day 60 target: [number] Day 60 target: [number] Destination of the gain: [text] Destination of the gain: [text] LIMITS (from the decision sheet): [what AI does not decide; which data does not go in] DECISION DATES, with the sponsor present Day 15 [date]: owner, baseline, approved tool, written limit. Something missing? It does not start. Day 30 [date]: test with [quantity] real cases in a small group. Errors seen: [record] Day 60 [date]: measurement against target, in a sample of [quantity]. Go on, pause or close. Day 90 [date]: expand, adjust or close, with the calculation of captured gain and total cost. WE STOP At once: [harm to a person; personal data outside the approved tool; other] For quality: rework above [%] in a sample of [quantity] For value: measured gain below [half of the target] on day 60 Who switches it off: [name] or [substitute], within [minutes]. Manual process: [where it is] FIRST SIGNS OF FAILURE: [sign, week, who watches]